The day our total station went dead mid-layout and I had to eat crow
Mid layout of a 40 unit apartment slab in Fresno last week, our total station battery died because nobody charged the spare, and instead of calling it I pulled out the old tape and string lines and got the first two walls within an eighth. Foreman still gave me grief about the delay, but it made me wonder why so many crews treat the robot as the only way to lay out. Do you keep a manual fallback plan on site or just hope the batteries hold?