Pour went sideways in Tempe when the ready mix showed up 90 minutes late
We were finishing a 40 by 60 slab for a patio cover in Tempe last month and the second truck rolled in an hour and a half behind schedule. The first load had already started to set at the edges, so when the second chute opened we got a cold joint right through the middle that you could feel with a trowel. I had two guys start wetting and working the edge while I ran a vibrator along the seam to try and knit it back together, and we burned an extra hour floating it out. It held up after curing but the color is slightly off in one strip and I still wonder if I should have just cut a control joint there instead. How do you all handle a late truck when the first pour is already going hard on you?